Installation
Operation
Maintenance
RTUB 207-224 - Liquid chillers with
helical rotary compressors
RTCA 108-216 - Remote air-cooled
condenser
RLC-SVX03A-E4
Download from Www.Somanuals.com. All Manuals Search And Download.
Contents
Foreword
2
2
2
2
2
Warranty
Reception of unit
Cautions and warnings
Refrigerant
General information
Unit Inspection
5
5
6
6
7
8
Inspection Checklist
Loose Parts Inventory
Description of the Unit
General Data RTUB
General Data RTCA
Installation
Installation Responsibilities
Storage
9
9
Special Lifting and Moving Instructions
Isolation
10
10
10
11
12
12
12
13
13
14
14
14
15
Foundation
Clearances
Drainage
Releasing the Nitrogen Holding Charge
Water Connections (RTUB)
Flow Switch Installation
Water Pressure Gauges
Refrigeration Safety Valves
Water Pressure Relief Valves
Installing and ConnectingTemperature Sensors
Connecting RTUB with the Remote Air-cooled Condenser
RLC-SVX03A-E4
3
Download from Www.Somanuals.com. All Manuals Search And Download.
Contents
Operation
Pre-start Checkout
21
21
21
21
22
22
22
23
23
23
23
Unit Voltage Power Supply
Unit Voltage Imbalance
Unit Voltage Phasing
Water System Flow Rates
Water System Pressure Drop
Daily Unit Start-up Procedure
Seasonal Unit Start-up Procedure
Temporary Shutdown and Restart
Extended Shutdown Procedure
System Restart after Extended Shutdown
Maintenance
Periodic Maintenance
25
27
28
28
29
29
29
Refrigerant and Oil Charge Management
R134a Field-charging Procedure
Charge Isolation on the High or Low Side of the System
Filter Replacement Procedure
Lubrication System
Oil Charging Procedure
Safety Recommendations
Maintenance Contract
Training
32
32
32
4
CG-PRC010-E4
Download from Www.Somanuals.com. All Manuals Search And Download.
General information
This manual describes installation,
operation, and maintenance of RTUB
and RTCA units.
A separate manual is available for
the use and maintenance of the
RTUB controls (UCM-CLD).
Unit Inspection
When the unit is delivered, verify
that it is the correct unit and that it is
property equipped. Compare the
information that appears on the unit
nameplate with the ordering and
submittal information. A typical unit
nameplate is shown in Figure 1.
Inspect all exterior components for
visible damage. Report any apparent
damage or material shortage to the
carrier and make a "unit damage"
notation on the carrier's delivery
receipt. Specify the extent and type
of damage found and notify the
appropriateTrane Sales Office. Do
not proceed with installation of a
damaged unit without sales office
approval.
Inspection Checklist
To protect against loss due to
damage incurred in transit, complete
the following checklist upon receipt
of the unit.
• Inspect the individual pieces of the
shipment before accepting the unit.
Check for obvious damage to the
unit or packing material.
• Inspect the unit for concealed
damage as soon as possible after
delivery and before it is stored.
Concealed damage must be
reported within 15 days.
If concealed damage is discovered,
stop unpacking the shipment. Do not
remove damaged material from the
receiving location.Take photos of the
damage, if possible.The owner must
provide reasonable evidence that the
damage did not occur after delivery.
• Notify the carrier's terminal of the
damage immediately, by phone and
by mail. Request an immediate,
joint inspection of the damage with
the carrier and the consignee.
RLC-SVX03A-E4
5
Download from Www.Somanuals.com. All Manuals Search And Download.
General information
• Notify theTrane sales
been assembled and wired in the
representative and arrange for
repair. Do not repair the unit,
however, until damage is inspected
by the carrier's representative.
factory.The discharge piping is
blocked at the oil separator outlet.
Water connections - chilled water
inlet and outlet - are blocked for
transportation. Both RTUB and RTCA
units are dried and vacuum-pumped
in the factory, and contain a nitrogen
holding charge when shipped.
Loose Parts Inventory
Check all the accessories and loose
parts that are shipped with the unit
against the shipping list. Included in
these items will be water vessel
drain plugs, rigging and electrical
diagrams, and service literature,
which are placed inside the control
panel and/or starter panel for
shipment.
Description of the Unit
The RTUB units are liquid chillers
equipped with two helical rotary
compressors and an evaporator
designed to operate with remote
RTCA air-cooled condensers or other
manufacturers' remote condensers.
The RTUB is shipped once it has
Figure 1 -Typical Unit Nameplates
RTUB
RTCA
é
6
RLC-SVX03A-E4
Download from Www.Somanuals.com. All Manuals Search And Download.
General information
Table 1 - General data - RTUB
Unit size
207
208
210
211
212
214
Compressor
Type/quantity
Helical rotary/2
Nominal size
(tons)
35/35
40/40
50/50
60/50
60/60
70/70
Evaporator
Evaporator Model
Water Storage
Minimum Flow
EG 120
105
4.5
EG 120
105
4.5
EG 140
365
6.0
EG 170
220
7.0
EG 170
220
7.0
EG 200
200
9.0
(l)
(l/s)
Maximum Flow
Evaporator inlet diameter
Evaporator outlet diameter
Minimum Starting/
Operating Ambient
Refrigerant
(l/s)
(inches)
(inches)
13.4
5
5
13.4
5
5
18.0
6
6
21.0
6
6
21.0
6
6
25.0
6
6
(°C)
5
R134a
Number of Independent
Refrigerant Circuits
Percent Minimum Load
Refrigerant Charge
Oil Charge
2
17
(%)
(kg)
(l)
26
12
26
12
40
14
40
14
40
14
40
16
Operating Weight
Shipping Weight
(kg)
(kg)
2130
1860
2130
1860
2845
2570
2845
2570
2845
2570
3250
2975
Unit size
216
217
218
220
222
224
Compressor
Type/Quantity
Helical rotary/2
Nominal size
(tons)
70/85
85/85
100/85
100/100
120/100
120/120
Evaporator
Evaporator Model
Water Storage
Minimum Flow
Maximum Flow
Evaporator inlet diameter
Evaporator outlet diameter
Minimum Starting/
Operating Ambient
Refrigerant
EG 200
200
9.0
25.0
6
EG 200
200
9.0
25.0
6
EG 250
415
11.0
33.0
6
EG 250
415
11.0
33.0
6
EG 340
560
14.0
43.0
6
EG 340
560
14.0
43.0
6
(l)
(l/s)
(l/s)
(inches)
(inches)
6
6
6
6
6
6
(°C)
5
R134a
Number of Independent
Refrigerant Circuits
Percent Minimum Load
Refrigerant Charge
Oil Charge
2
(%)
(kg)
(l)
17
46
16
40
16
40
16
46
16
50
19
50
22
Operating Weight
Shipping Weight
(kg)
(kg)
3250
2975
3250
2975
3880
3405
4050
3575
4480
3855
4550
3925
RLC-SVX03A-E4
7
Download from Www.Somanuals.com. All Manuals Search And Download.
General information
Table 2 - General data - RTCA
Unit size
108
109
111
113
115
116
Condenser
Condenser type
Fin spacing
Frontal surface area
Airflow
Aluminium fins/copper tubes
(fins/ft)
(m²)
168
5.7
168
6.9
144
6.9
168
11.3
168
11.7
144
13.7
3
Standard unit
(m /h)
42500
34500
50400
40900
69300
56300
77200
62700
84700
68800
98500
80000
3
Low noise unit
Condenser fans
Number of fans
Fan speed
(m /h)
4
4
6
8
8
12
Standard unit
(rpm)
(rpm)
690
560
Low noise unit
Nominal fan power
Standard unit
Low noise unit
Current fan amps
Standard unit
Low noise unit
Minimum Starting/
Operating Ambient (1)
Refrigerant
(kW)
(kW)
0.85
0.54
(A)
(A)
2.4
1.2
(°C)
7 Standard units/-18 Low ambient units
R134a
Number of Independent
Refrigerant Circuits
Refrigerant Charge
Operating Weight (2)
Shipping Weight (2)
Hot gas connection
Liquid connection
1
22
810
1020
1 5/8
1 1/8
1
26
890
1100
1 5/8
1 1/8
1
36
1090
1300
1 5/8
1 1/8
1
44
1535
1870
1 5/8
1 1/8
1
52
1770
2170
1 5/8
1 1/8
1
72
2050
2450
1 5/8
1 1/8
(kg)
(kg)
(kg)
(inches)
(inches)
Unit size
208
209
211
213
215
216
Condenser
Condenser type
Fin spacing
Frontal surface area
Airflow
Aluminium fins/copper tubes
(fins/ft)
(m²)
168
5.7
168
6.9
144
6.9
168
11.3
168
11.7
144
13.7
3
Standard unit
(m /h)
42500
34500
50400
40900
69300
56300
77200
62700
84700
68800
98500
80000
3
Low noise unit
Condenser fans
Number of fans
Fan speed
(m /h)
2 x 2
2 x 2
2 x 3
2 x 4
2 x 4
2 x 6
Standard unit
(rpm)
(rpm)
690
560
Low noise unit
Nominal fan power
Standard unit
Low noise unit
Current fan amps
Standard unit
Low noise unit
Minimum Starting/
Operating Ambient (1)
Refrigerant
(kW)
(kW)
0.85
0.54
2.4
1.2
(°C)
7 Standard units/-18 Low ambient units
R134a
Number of Independent
Refrigerant Circuits
Refrigerant Charge
Operating Weight (2)
Shipping Weight (2)
Hot gas connection
2
2
2
2
2
2
(kg)
(kg)
(kg)
(inches)
2 x 11
810
1020
1 5/8
1 1/8
2 x 13
890
1100
1 5/8
1 1/8
2 x 18
1090
1300
1 5/8
1 1/8
2 x 22
1535
1870
1 5/8
1 1/8
2 x 26
1770
2170
1 5/8
1 1/8
2 x 36
2050
2450
1 5/8
1 1/8
Liquid connection
(inches)
(1) Based on a 2.2 m/s wind across the condenser
(2) With aluminium fins
8
RLC-SVX03A-E4
Download from Www.Somanuals.com. All Manuals Search And Download.
Installation
• Install heat tape and insulate the
chilled-water lines and any other
portions of the system, as required,
to prevent sweating under normal
operating conditions or freezing
during low-ambient temperature
conditions.
Installation responsibilities
Generally, the contractor must do the
following when installing an
RTUB/RTCA unit.
• Install the units on a flat
foundation, level (within 1/4"
[6 mm] across the length of the
unit), and strong enough to support
unit loading.
• Start the unit under the supervision
of a qualified service technician.
• Install the units per the instructions
contained in the Installation section
of this manual.
Storage
If the chiller is stored for a long period
of time prior to installation, the
following precautionary measures must
be taken:
• Install any optional sensors and
make electrical connections at the
UCM-CLD.
• Store the unit in a safe place
sheltered from bad weather
• Where specified for the RTUB,
provide and install valves in the
water piping upstream and
downstream of the evaporator
water connections, to isolate the
evaporator for maintenance and to
balance and trim the system.
• At least every three months
(quarterly), check the pressure in
the refrigerant circuits to verify that
the nitrogen holding charge is
intact. If it is not, contact a qualified
service organization and the
• Furnish and install a flow switch
and/or auxiliary contacts to prove
chilled-water flow.
appropriateTrane sales office.
• Close the discharge and liquid-line
isolation valves.
• Furnish and install pressure gauges
in the inlet and outlet piping of the
evaporator (for RTUB).
• Furnish and install a drain valve to
the bottom of the evaporator water
box (for RTUB).
• Supply and install a vent cock to the
top of the evaporator water box (for
RTUB).
• Furnish and install strainers ahead
of all pumps and automatic
modulating valves.
• Furnish and install check valves on
the discharge lines (between oil
separators and condenser) in order
to avoid any refrigerant migration
leading to catastrophic damages to
evaporator and/or compressor (due
to freeze-up or liquid slugging).
• Interconnect the RTUB and the
remote condenser.
• Provide and install field wiring.
RLC-SVX03A-E4
9
Download from Www.Somanuals.com. All Manuals Search And Download.
Installation
Figure 2- Rigging the unit - RTUB 207-208
Figure 3- Rigging the unit - RTUB 210-224
Figure 4- Rigging the unit - RTCA 108-216
Table 3 - Sling Lengths (mm) for lifting
A
B
C
D
E
RTUB unit size
207-208
210-211-212
214-216-217
218-220
2200
2400
2500
2450
2450
3000
3000
3000
3050
3100
2600
2550
2550
2600
2650
2100
3150
3150
3150
3150
-
3650
3650
3650
3650
222-224
RTCA unit size
108/109/111/208/209/211
113/115/115/213/215/216
2240
2240
1700
2800
1700
2800
-
-
-
-
conduit, use flexible electrical
conduit. State and local codes on
sound emissions should always be
considered.
Special Lifting and Moving
Instructions
ƽ WARNING
To prevent any damage, position the
lifting bar so that the slings do not
touch the unit.
A specific lifting method is
recommended as follows:
1. Four lifting points are built into the
unit.
Foundation
Provide rigid, non-warping mounting
pads or a concrete foundation of
sufficient strength and mass to
support the unit's operating weight
(that is, including completed piping,
and full operating charges of
Isolation
2. Slings and spreader bar to be
provided by rigger and attached to
the four lifting points.
The most effective form of isolation
is to locate the unit away from any
sound-sensitive area. Structurally
transmitted sound can be reduced by
elastomeric vibration eliminators.
Spring isolators are not
3. Minimum rated lifting capacity
(vertical) of each sling and
spreader bar shall be no less than
the tabulated unit shipping weight.
refrigerant, oil, and water). After it is
in place, the unit must be level
within 1/4" [6 mm] over its length
and width. Use shims if necessary.
The manufacturer is not responsible
for equipment problems resulting
from an improperly designed or
constructed foundation.
Note for RTCA:The unit must be
positioned so that the airflow
through the condensation coils is not
hindered by any obstacle.The
recommended for units equipped
with helical rotary compressors.
Consult an acoustical engineer in
critical sound applications. For
maximum isolation effect, isolate
water lines and electrical conduit.
Wall sleeves and rubber- isolated
piping hangers can be used to
reduce the sound transmitted
ƽ CAUTION
This unit must be lifted with the
utmost care. Avoid shock load by
lifting slowly and evenly.
through water piping.To reduce the
sound transmitted through electrical
10
RLC-SVX03A-E4
Download from Www.Somanuals.com. All Manuals Search And Download.
Installation
condensation coils must be
dimensions and recommended
clearances. Unobstructed flow of
condenser air is essential to maintain
chiller capacity and operating
efficiency.
protected from side winds when
their speed exceeds 16 km/h.
Position the unit above the average
height of snow observed in the
region where it is installed. Never
install temporary or permanent
objects (tarp or roof) over the unit,
because recycling of hot air would
reduce the capacity of the
Note for RTCA: When determining
unit placement, give careful
consideration to ensuring a sufficient
flow of air across the condenser
heat-transfer surface.
condensation coils. Discharged air
from the fans must not be
obstructed. It is prohibited to install
ducts for the fan discharge air (even
short ones).This is because the fans
supplied on standard units do not
generate any additional static
pressure.
Clearances
Provide enough space around the
unit to allow the installation and
maintenance personnel unrestricted
access to all service points. Refer to
Figure 5 andTable 4 for unit
Figure 5: Unit Dimensions and
Recommended Minimum
Clearances - RTCA
Figure 6: Unit Dimensions and
Recommended Minimum
Clearances - RTUB
C
D
B
B
A
A
D
C
Table 4 - Unit Dimensions and Recommended Minimum Clearances (mm)
Length
2870
4610
5450
2880
4150
4150
4150
Width
2285
2285
2285
890
890
890
890
Height
1630
1630
1630
1789
1832
1932
2041
A
B
C
D
RTCA 108/109/111/208/209/211
RTCA 113/213
RTCA 115/116/215/216
RTUB 207/208
RTUB 210/211/212/214/216/217
RTUB 218/220
RTUB 222/224
1000
1000
1000
950
950
950
1000
1000
1000
800
800
800
1000
1000
1000
1800
2750
2750
2750
1000
1000
1000
500
500
500
950
800
500
RLC-SVX03A-E4
11
Download from Www.Somanuals.com. All Manuals Search And Download.
Installation
boxes that can lead to premature
failure of the water box.
Drainage
ƽ CAUTION
Provide a large-capacity drain for
water vessel drain-down during
shutdown or repair.The evaporator
is provided with a drain connection.
All local and national codes apply.
The vent on the top of the
A vent line is located on the top part
of the evaporator at the water return
piping end. Install additional vent
lines at the highest points in the
piping to vent the air present in the
chilled water circuit. Install
manometers to monitor the pressure
of chilled water entering and leaving
the evaporator.
Install a strainer in the evaporator-
water inlet piping. Failure to do so
can result in evaporator tube
damage.
Leaving Chilled-Water Piping
evaporator water box is provided to
prevent a vacuum, by allowing air
into the evaporator for complete
drainage.
• Air vents (to bleed air from system).
• Water pressure gauges with shutoff
valves.
• Vibration eliminators.
• Shutoff (isolation) valves.
•Thermometers (if desired).
• Clean out tees.
ƽ CAUTION
To prevent damage to chilled-water
components, do not allow
evaporator pressure (maximum
working pressure) to exceed 10.5
bars.
Releasing the Nitrogen
Holding Charge
The nitrogen holding charge can be
released into the atmosphere.
• Balancing valve.
ƽ CAUTION
When releasing nitrogen holding
charge, ventilate the room. Avoid
breathing in the nitrogen.
Provide shutoff valves in lines to the
gauges, in order to isolate them from
the system when they are not in use.
Use rubber vibration eliminators to
prevent vibration transmission
through the water lines. If desired,
install thermometers in the lines to
monitor entering- and leaving-water
temperatures. Install a balancing
valve in the leaving-water line to
control water flow balance. Install
shutoff valves on both the entering-
and leaving-water lines so that the
evaporator can be isolated for
service. A pipe strainer must be
installed in the entering water line.
Failure to do so can allow
• Flow Switch
Evaporator Drain
A 3/4" drain connection is located
under the outlet end of the
evaporator water box.This may be
connected to a suitable drain to
permit evaporator drainage during
unit servicing. A shutoff valve must
be installed on the drain line.
Water Connections (RTUB)
Thoroughly flush all water piping to
the unit before making the final
piping connections to the unit.
ƽ CAUTION
Evaporator Flow Switch (accessory)
The chilled water flow is protected
by the UCM-CLD without the
assistance of a chilled water flow
switch.The flow switch is optional,
but if it is not installed, a signal must
be sent to the chiller to indicate the
water flow is established, for
example the auxiliary contacts of the
chilled water pump starter.
If additional protection of the chilled
water flow proves necessary,
connect a flow switch installed on
site, or a differential pressure switch
to control the system's water flow.
Connect the flow switch in series
with the auxiliary contacts of the
chilled water pump motor starter. A
special connector is supplied with
the unit, with the wiring diagrams.
Some piping and control schemes,
particularly those using a single
water pump for both chilled- water
and hot water, must be analyzed to
determine how and/or if a flow-
sensing device will provide the
desired operation.
If using an acidic commercial
flushing solution, construct a
temporary bypass around the unit to
prevent damage to internal
components of the evaporator.To
avoid possible equipment damage,
do not use untreated or improperly
treated system water.
When making the water connections,
use flange connectors. Insulate all
piping to reduce temperature
increases and to prevent
condensation. Figure 7 shows all the
piping systems for the evaporator
and its components.The
waterborne debris to enter the
evaporator.
"Piping components" include all
devices and controls used to provide
proper water system operation and
unit operating safety.These
components and their general
locations are given in Figure 7.
Entering Chilled-Water Piping
arrangement of the pipes and the
other components varies slightly
according to the positioning of the
connections and the water source.
• Air vents (to bleed air from system).
• Water pressure gauges with shutoff
valves.
• Vibration eliminators.
• Shutoff (isolation) valves.
•Thermometers (if desired).
• Clean out tees.
ƽ CAUTION
The chilled water connections to the
evaporator are Victaulic connections.
Do not attempt to weld these
connections, because the heat
generated from welding can cause
microscopic and macroscopic
fractures on the cast- iron water
• Pipe strainer.
12
RLC-SVX03A-E4
Download from Www.Somanuals.com. All Manuals Search And Download.
Installation
Follow the manufacturer's
instructions for the installation
procedures.
4. Install a pipe strainer in the
entering evaporator-water line to
protect components from
waterborne debris.
use inTrane units. Use of either will
lead to a shortened life to an
indeterminable degree.TheTrane
Company encourages the
employment of a reputable water
treatment specialist, familiar with
local water conditions, to assist in
this determination and in the
establishment of a proper water-
treatment program.
Flow Switch Installation
1. Mount the switch upright, with a
minimum of 5 pipe diameters of
straight horizontal run on each
side. Do not install close to
elbows, orifices, or valves. Note:
The arrow on the switch must
point in the direction of flow.
WaterTreatment
ƽ CAUTION
If calcium chloride is used for waste
treatment, an applicable corrosion
inhibitor must also be used. Failure
to do so may result in damage to
system components. Dirt, scale,
products of corrosion, and other
foreign material will adversely affect
heat transfer between the water and
system components. Foreign matter
in the chilled-water system can also
increase pressure drop and,
consequently, reduce water flow.
Proper water treatment must be
determined locally, depending on the
type of system and local water
characteristics. Neither salt nor
brackish water is recommended for
Water Pressure Gauges
Install field-supplied pressure
components as shown in Figure 7.
Locate pressure gauges or taps in a
straight run of pipe; avoid placement
near elbows, and so forth. Be sure to
install the gauges at the same
elevation on each shell if the shells
have opposite-end water
connections. Note: After the unit is
installed at a site, one vertical (or one
diagonal) unit support can be
2.To prevent switch fluttering,
remove all air from the water
system. Note:The UCM-CLD waits
for six seconds after a “flow loss”
diagnosis before stopping the unit.
Contact a qualified service
representative if nuisance machine
shutdowns persist.
3. Adjust the switch to open when
water flow falls below nominal.
Evaporator data is given inTable 1.
Flow-switch contacts are closed on
proof of water flow.
permanently removed if it creates an
obstruction for water piping.To read
Figure 7 -Typical piping of the evaporator (RTUB)
1 Air vent
2 Balance valve
3 Flow switch
4Thermometers
5 Expansion joints
6 Stop valves
7 Manometer
8 Evaporator
9 Filter
7
3
8
2
10 Drainage
6
5
1
4
6
9
10
RLC-SVX03A-E4
13
Download from Www.Somanuals.com. All Manuals Search And Download.
Installation
Figure 8- RTUB Evaporator water pressure drops
Evaporator Water Pressure Drop
Water Flow Rate l/s
the values given by the pressure
gauges, open one valve and close
the other.
Install the sensor at 4 o'clock on the
water piping to prevent any
Water Pressure-Relief
Valves
condensation. When installing
standard or optional temperature
sensors described in the following
paragraphs, comply with the
instructions:
Put thermocontact paste in each
sensor bulbwell before inserting the
sensor. All the temperature sensors
installed on site have an
identification number and a serial
number marked on the part body.
Also note that both sensors in each
pair have the same serial number.
ƽ CAUTION
To prevent shell damage, install
pressure-relief valves in the
Refrigerant SafetyValves
Discharge valves are an option for
the RTUB. If installation requires this
valve to be mounted, it is mandatory
to install two safety valves: one
between the compressor and the
service valve and the other after the
service valve to protect the
evaporator water system. Install a
water pressure-relief valve in the
evaporator inlet piping, between the
evaporator and the inlet shutoff
valve. Water vessels with close-
coupled shutoff valves have a high
potential for hydrostatic pressure
buildup on a water temperature
increase. Refer to applicable codes
for relief-valve installation
condenser.
ƽ CAUTION
The safety valve calibration must not
exceed 25 bars.The liquid line must
be connected at the inlet to the drier
filter which is supplied with a bend
blocked by a brazed plug.The
connection piping must be correctly
dimensioned and installed, because
these factors have a substantial
impact on the system's performance
and reliability.
ƽ WARNING
guidelines.
To prevent degraded operation due
to electrical interference, run the
sensor cables in a duct. However, do
not lay sensor cables with other
cables whose voltage is greater than
30 VAC.
Installing and connecting
temperature sensors
General Recommendations
Regardless of the type of monitoring
sensor required by a particular
application, the sensor must always
be positioned far enough from the
evaporator or condenser to enable
the sensor to read a correct
Extension of sensor power cable
A temperature sensor's power cable
may not be long enough to reach the
UCM. If this is the case for your
installation, connect the cable to a
junction box installed in a more
temperature for the mixed water.
14
RLC-SVX03A-E4
Download from Www.Somanuals.com. All Manuals Search And Download.
Installation
convenient position. Plug the sensor
cable and the cable connected to the
control panel into the junction box.
The shielded cable can be cut to the
required length.
correctly, refer to the general
recommendations. Connect the
outside air sensor 5R3 to terminals 1
and 2 on terminal board 1. Connect
the condenser sensor 5R56-1 to
terminals 4 and 5 on terminal board
J4 on module A20-1. Connect the
condenser sensor 5R56-2 to
withstanding high temperatures
without degradation.
ƽ CAUTION
A defect in fixing or insulating the
condensation sensors may cause
incorrect adjustment and/or damage
to the compressor.
Note:To lengthen the sensor's power
cable, use 0.75 to 1.25 mm²
conductors, 600V.The cable used
between the junction box and the
control panel must either be shielded
or in a duct. If a shielded cable is
used, make sure it is not used with
other cables carrying 30 V or more.
terminals 4 and 5 on terminal J4 on
module A20-2.
If the sensor cannot be mounted in
the place where the saturated gas
enters the sub-cooler, it must be
positioned on the sub-cooler side
and not on the condenser side. If the
condenser temperature cannot be
measured, it is preferable to
measure the liquid temperature
instead of the discharge
If the condenser is not an RTCA,
ambient temperature and condenser
temperature sensors must be
connected to the RTUB to monitor it.
The ambient temperature sensor
must be installed in a position which
represents most accurately the
condenser's surrounding
environment. It must not be exposed
to sunlight or precipitation. Ensure
that the sensor is not located in the
flow of recycled air from the
Evaporator leaving water
temperature sensor 5R51 (standard)
Install this temperature sensor in the
evaporator's leaving water piping
system.To install it correctly, refer to
the general recommendations.
Connect this sensor to terminals
X7-1 and X7-2.
temperature.
ƽ CAUTION
To prevent interference, separate the
sensor cables from the power cables.
Evaporator entering water
temperature sensor 5R52 (standard)
Install this sensor in the evaporator
water piping.To install it correctly,
refer to the general
recommendations. Connect this
sensor across terminals X6-1 and
X6-2.
condenser discharge.The
condensation temperature sensors
must be installed on the refrigerant
piping at the place where it leaves
the condenser to enter the sub-
cooler. It is necessary to install a
condenser temperature sensor on
each refrigerant circuit.This sensor
must be fixed in compliance with the
method used to attach the bulb for a
thermostat expansion valve.This
sensor can be fixed outside the
piping if it is sufficiently insulated
with insulation capable of
Electrical connections
performed by the installer
All wiring must comply with local
codes. Specific electrical schematics
and connection diagrams are
shipped with the unit.
Condenser sensors 5R56-1, 5R56-2,
5R3 (option)
ƽ CAUTION
If an RTCA condenser is used with an
RTUB, the sensors required are
installed on the RTCA.To install them
To avoid corrosion and overheating
at terminal connections, use copper
conductors only. Failure to do so
may result in damage to the
equipment. Do not allow conduit to
interfere with other components,
structural members or equipment.
Control voltage (110 V) wiring in
conduit must be separate from
conduit carrying low voltage (<30 V)
wiring.To prevent control
Figure 9: UCM water temperature sensor installation
7
6
malfunctions, do not run low voltage
wiring (<30 V) in conduit with
conductors carrying more than 30 V.
5
4
Connecting the RTUB with a remote
air-cooled condenser
2
1
The RTUB unit is shipped with a
holding nitrogen charge and a
separate oil charge.The RTCA
condenser is designed to operate
with the RTUB unit.To ensure
optimum operation and
3
1 In
5 Compression fitting (Trane-supplied)
6 Fitting body
7 Clamping nut
performance, the RTUB must be
installed with the RTCA condenser. If
2 Out
3 UCM sensor
4 ¼" NPT coupling (customer-supplied)
RLC-SVX03A-E4
15
Download from Www.Somanuals.com. All Manuals Search And Download.
Installation
Figure 10 - Detail of positions of refrigerant sensors 5R56-1 and 5R6-2
another manufacturer's condenser in
used, operation and performance
may be degraded. Depending on the
fan settings, malfunctioning may
damage the RTUB due to instability
of the high pressure.
3
2
1
Sound and vibration attenuating
device installation on the discharge
lines is strongly recommended in
order to avoid any acoustical
annoyance and distubing vibrations
leading to discharge line failures.
57
ƽ WARNING
1 Sensor
2 Connector
3 Brazed connector on the condenser
If the condenser connected to a dual-
circuit RTUB is not an RTCA, it must
comprise two refrigerant circuits,
each with its own ventilation.The
ventilation cannot be common to the
two circuits.
For this type of installation, (non-
RTCA condenser), an On/Off signal is
available on the unit control module
(UCM) of the RTUB for each
refrigerant circuit, indicating whether
the fans on each condenser circuit
are on or off.The now autonomous
control of the fan on each condenser
circuit must comprise the following
staging:
For an ambient temperature between
0 and 40°C, there must be four
airflow control stages for each circuit
(i.e. 25% of the nominal airflow in
each stage).
16
RLC-SVX03A-E4
Download from Www.Somanuals.com. All Manuals Search And Download.
Installation
Figure 11: Units on the same level
1
2
Limitations:The distance between the two units must not exceed 60 m in reality or the equivalent of 90 m taking into
account pressure drops.The height of the liquid line in relation to the unit base must be less than 5 m. It is
recommended to place a trap on the discharge line at the oil separator outlet, if this discharge line is horizontal for a
distance greater than 5 m, at a height greater than the connection to the oil separators.
Figure 12: RTCA (or other manufacturer's condenser) above the RTUB
4
Limitations:The distance between the two units must not exceed 60 m in reality or the equivalent of 90 m taking into
account pressure drops. Each 30 m level difference causes a 2% efficiency loss.
RLC-SVX03A-E4
17
Download from Www.Somanuals.com. All Manuals Search And Download.
Installation
Figure 13: RTCA (or other manufacturer's condenser) below the RTUB
3
Limitations:The distance between the two units must not exceed 60 m in reality or the equivalent of 90 m taking into
account pressure drops.The height of the liquid line in relation to the condenser base must be less than 5 m.
Legend for Figures 11-12-13:
1 Discharge line connections
2 Liquid line connections
3Trap
4 Counter-trap
18
RLC-SVX03A-E4
Download from Www.Somanuals.com. All Manuals Search And Download.
Installation
Equivalent pressure drops
To correctly determine the size of the
liquid and discharge lines for
connection on site, it is first
necessary to establish the equivalent
pressure drops for each line,
The minimum slope of the suction
line to the condenser must be 5%.
Isolate refrigerant fluid lines from the
building to prevent the vibrations
normally generated by the ducts
from being transmitted to the
comprising the additional flow
resistances, from bends, valves, etc.
As a first approximation, we can
estimate the equivalent pressure
drops at 1.5 times the piping length.
building's structure. Also avoid
bypassing the unit's isolation system
by fixing the refrigerant fluid lines or
the electrical ducts very rigidly. Any
vibrations may be propagated into
the building via rigid piping or lines.
Size of the liquid line
The standpipe must not be more
than 5 m above the air-cooled
condenser base. It is not necessary
to slope the liquid line. It is
recommended to have a line
diameter as small as possible, while
maintaining an acceptable pressure
drop so as to minimize the
refrigerant charge (length and
maximum pressure drops defined
above).
Pressure tests and leak
detection
ƽ WARNING
During these operations, take the
following precautions:
1. Do not use oxygen or acetylene
instead of the refrigerant fluid and
nitrogen to detect leaks.This may
cause a violent explosion.
Determine the size using the
following criteria:
1. Operating conditions with full load
2. Always use the expansion valve,
safety valves and manometers to
control the test pressure in the
system. Excessive pressure may
cause piping to rupture, damage
the unit or cause explosion
2. Maximum pressure drops of
100-kPa
3. Liquid speed not exceeding 3 m/s
(to prevent liquid shocks)
resulting in personal injury.
In normal operating conditions
(suction temperature 4.5°C,
condenser air inlet temperature 35°C
or condensation temperature of
52°C), the liquid leaving the
condenser is sub-cooled by
approximately 10°C.Take this value
as a basis to determine the
maximum permitted pressure drops,
and use it to calculate the liquid line
pressure drops.
Carry out the liquid line and hot gas
line pressure tests using the
standards in force.The test pressure
applied to the liquid line and the
discharge line must comply with
local regulations. Insert enough
refrigerant fluid into the circuit to
obtain a pressure of 1 bar.
By injecting dry nitrogen using a
pump, increase this pressure to
7 bars. Look for leaks in the entire
system using a detector.
If leaks are detected, evacuate the
fluid from the system and repair the
defective component. Repeat the test
process to check the repair is
watertight.
Discharge line
Install them so as to obtain a gas
speed in the horizontal and vertical
lines making it possible to carry
along the compressor oil. Determine
the dimensions of the suction line
using the following criteria:
1. 2.5 m/s (minimum) in the
horizontal parts
2. 5.0 m/s (minimum) in the vertical
parts
3. Maximum speed 20 m/s
RLC-SVX03A-E4
19
Download from Www.Somanuals.com. All Manuals Search And Download.
Installation
Vacuum pumping
Do not use rubber or synthetic pipes
which retain humidity, increase the
duration of the vacuum pumping
and cause pressure rises during the
vacuum tests. An electronic vacuum
measurement manometer must be
installed upstream of the vacuum
pump stop valve.
1. Close valve B and open valve A.
After a few minutes, the
manometer reading indicated the
lowest vacuum level that can be
obtained by the pump.
For this operation, use a vane pump
making it possible to obtain a partial
vacuum or 100 microns or less.
When pumping out to create a
vacuum, it is important to connect
the pump to the high and low
pressure sides of the system. Follow
the pump manufacturer's
recommendations.The pipes used to
connect the pump to the system
must be made of copper, with the
largest diameter possible. A large
pipe diameter reduces flow
2. Open valve B and operate the
vacuum pump until 1500 Hg
microns (0.67 mbar) or less is
obtained. Close valve A when you
read the manometer.
resistance and shortens the duration
of the vacuum pumping.
3. Once the value of 500 microns or
less has been reached and valve A
has been closed, the pressure will
rise.
The maximum permissible increase
is 200 microns after 15 minutes. If
this limit is exceeded and the value
remains constant, there is too much
humidity in the system. A continuous
increase in pressure indicates there
is a leak in the system.
Figure 14 -Vacuum pump connection
2
1
4
6
5
3
1 Header
2Valve B
3Vacuum pump
4Vacuum manometer
5Valve A
6 Low pressure side
7 High pressure side
7
20
RLC-SVX03A-E4
Download from Www.Somanuals.com. All Manuals Search And Download.
Operation
Do not use untreated or improperly-
treated water. Equipment damage
may occur.
• Energize the compressor and oil
separators 24 hours prior to unit
startup.
Pre-start checkout
Installation Checklist
When installation is complete, but
prior to putting the unit into service,
the following pre-start procedures
must be reviewed and verified:
• Fill the evaporator chilled-water
circuit. Vent the system while it is
being filled. Open the vents on the
top of the evaporator water box
while filling and close when filling
is completed.
UnitVoltage Power Supply
Voltage to the unit must meet the
criteria given in the Installation
section. Measure each leg of the
supply voltage at the main power
fused-disconnect switch for the unit.
If the measured voltage on any leg is
not within the specified range, notify
the supplier of the power and correct
the situation before operating the
unit.
• Inspect all wiring connections to be
sure they are clean and tight.
The use of improperly-treated or
untreated water in this equipment
may result in scaling, erosion,
corrosion, algae, or slime.The
services of a qualified water-
ƽ WARNING
Disconnect all electric power,
including remote disconnects, before
servicing. Failure to disconnect
power before servicing can cause
severe personal injury or death.
treatment specialist should be
engaged to determine what
ƽ CAUTION
treatment, if any, is advisable.Trane's
warranty specifically excludes
liability of corrosion, erosion, or
deterioration ofTrane equipment.
Trane assumes no responsibilities for
the results of the use of untreated or
improperly-treated water, or saline or
brackish water.
Provide adequate voltage to the unit.
Failure to do so can cause control
components to malfunction and
shorten the life of relay contact,
compressor motors and contactors.
ƽ CAUTION
• Check the tightness of all
connections in the compressor
power circuit (disconnects, terminal
block, contactors, compressor
junction box terminals,…). Loose
connections can cause overheating
at the connections and
UnitVoltage Imbalance
Excessive voltage imbalance
between the phases of a three-phase
system can cause motors to
overheat and eventually fail.The
maximum allowable imbalance is
2%. Voltage imbalance is determined
using the following calculations:
• Close the fused-disconnect
switch(es) that supplies power to
the chilled-water pump starter.
undervoltage conditions at the
compressor motor.
• Start the chilled-water pump to
begin circulation of the water.
Inspect all piping for leakage and
make any necessary repairs.
• Open all refrigerant valves in the
discharge, liquid, oil, and oil return
lines.
% Imbalance = [(Vx - V ave) x 100]/V
ave
ƽ CAUTION
• With water circulating through the
system, adjust the water flow and
check the water pressure drop
through the evaporator.
V ave = (V1 + V2 + V3)/3
Do not operate the unit with the
compressor, oil discharge, liquid-line
service valves, or the manual shutoff
on the refrigerant supply to the
auxiliary coolers "CLOSED." Failure
to have these "OPEN" may cause
serious compressor damage.
Vx = phase with the greatest
difference from V ave (without
regard to the sign)
• Adjust the chilled-water flow switch
for proper operation.
For example, if the three measured
voltages are 391, 407, and 402 volts,
the average would be:
ƽ WARNING
(391+407+402)/3 = 400
• Check the power-supply voltage to
the unit at the main-power fused-
disconnect switch. Voltage must be
within the voltage utilization range
and also stamped on the unit
nameplate. Voltage imbalance must
not exceed 2%.
Use extreme caution when
performing the following procedure
with power applied. Failure to do so
can result in personal injury or
death.
The percentage of the imbalance is
then:
[100(400-391)]/400 = 2.25%
This exceeds the maximum
allowable (2%) by 0.25%
• Reapply power to complete the
procedures.
UnitVoltage Phasing
• Check the unit power phasing L1-
L2-L3 in the starter to ensure that it
has been installed in an "A B-C"
phase sequence.
• Prove all Interlock and
It is imperative that L1, L2, and L3 in
the starter be connected in the A-B-C
phase sequence to prevent
equipment damage due to reverse
rotation.
Interconnecting Wiring Interlock
and External as described in the
Installation section.
ƽ CAUTION
Improper power phasing can result
in equipment damage due to reverse
rotation.
• Check and set, as required, all
UCM-CLD menu items.
It is important that proper rotation of
the compressors be established
before the unit is started. Proper
• Stop the chilled-water pump.
RLC-SVX03A-E4
21
Download from Www.Somanuals.com. All Manuals Search And Download.
Operation
motor rotation requires confirmation
of the electrical phase sequence of
the power supply.The motor is
internally connected for clockwise
rotation with the incoming power
supply phased A-B-C.
Do not interchange any load leads
that are from the unit contactors or
the motor terminals. Doing so may
damage the equipment.
control calls for cooling and all the
safety interlocks are closed, the unit
will start.The compressor(s) will
load and unload in response to the
temperature of the leaving chilled-
water temperature.
7. Reopen the unit disconnect and
disconnect the phase-sequence
indicator.
When rotation is clockwise, the
phase sequence is usually called
"ABC;" when counterclockwise,
"CBA."This direction may be
reversed outside the alternator by
interchanging any two of the line
wires. It is this possible interchange
of wiring that makes a phase
After the system has been operating
for approximately 30 minutes and
has become stabilized, complete the
start-up procedure as follows:
Water-System Flow Rates
Establish a balanced chilled-water
flow through the evaporator.The flow
rates should be between the
minimum and maximum values
given on the pressure-drop curves.
• Check the evaporator refrigerant
pressure and the condenser
refrigerant pressure in the
Refrigerant report of the UCM-CLD.
Water-System Pressure Drop
sequence indicator necessary if the
operator is to quickly determine the
phase rotation of the motor.
Measure the water-pressure drop
through the evaporator at the field-
installed pressure taps on the system
water piping. Use the same gauge for
each measurement. Do not include
valves, strainers, or fittings in the
pressure-drop readings.
• Measure the system overheat.
• Measure the system subcooling.
1. Press the Stop key on the UCM-
CLD.
A shortage of refrigerant is indicated
if the operating pressures and the
subcooling are low. If the operating
pressures, superheat, and
subcooling readings indicate a
refrigerant shortage, gas-charge
refrigerant into each circuit as
required. With the unit running, add
refrigerant vapor by connecting the
charging line to the suction service
valve and charging through the
backseat port until operating
2. Open the electrical disconnect or
circuit protection switch that
provides line power to the line-
power terminal block(s) in the
starter panel (or to the unit-
mounted disconnect).
Start-up Procedures
Daily Unit Start-up Procedure
When the verification operations
prior to start-up have been performed
(see previous sections), the unit is
ready to start.
3. Connect the phase-sequence
indicator leads to the line power
terminal block as follows:
Phase Sequence LeadTerminal
Black (Phase A) L1
conditions become normal.
• Press the Stop key on the UCM-CLD.
• If necessary, adjust the setpoint
values in the UCM-CLD reports
(refer to the UCM-CLD user guide).
ƽ WARNING
Red (Phase B) L2
If both suction and discharge
pressures are low and subcooling is
normal, a problem other than
refrigerant shortage exists. Do not
add refrigerant, as this may result in
overcharging the circuit.
Yellow (Phase C) L3
• Close the fused disconnect switch
for the chilled water pumps and the
cooling water pumps.
4.Turn power on by closing the unit
supply-power fused-disconnect
switch.
• Energize the pumps to start the
water circulation.
5. Read the phase sequence on the
indicator.The "ABC" LED on the
face of the phase indicator will
glow if the phase is "ABC."
Only use the refrigerant specified on
the unit nameplate.
• Check the service valves on the
discharge line, suction line, oil line
and liquid line for each circuit.
These valves must be open before
starting the compressors.
• If operating conditions indicate a
refrigerant overcharge, remove
refrigerant at the liquid line service
valve. Allow refrigerant to escape
slowly to minimize oil loss. Do not
discharge refrigerant into the
atmosphere.
ƽ WARNING
To prevent injury or death due to
electrocution, take extreme care
when performing service procedures
with electrical power energized.
ƽ WARNING
To prevent compressor damage, do
not operate the unit until all
refrigerant and oil-line valves are
opened.
6. If the "CBA" indicator glows
instead, open the unit main-power
disconnect and interchange two
line leads on the line-power
terminal block(s) (or the unit-
mounted disconnect). Close the
main-power disconnect and
recheck the phasing.
ƽ WARNING
Do not allow refrigerant to directly
contact skin, or injury from frostbite
may result.
• Verify that the chilled water pump
runs for one minute after the chiller
is commanded to stop for normal
chilled water systems).
Overheating
Normal overheating for each circuit
is approximately 3-4°C at full
• Press the Auto key. If the chiller
22
RLC-SVX03A-E4
Download from Www.Somanuals.com. All Manuals Search And Download.
Operation
operating load. Overheating may
vary slightly on the circuit if the
system load is lower, when the slide
valve is moving.
and damage to the system when it
has been set up for extended
shutdown.
Shutdown procedures
Temporary Shutdown and Restart
To shut the unit down for a short
time, use the following procedure:
5. At least every three months
(quarterly), check the refrigerant
pressure in the unit to verify that
the refrigerant charge is intact.
Overheating must stabilize at
approximately 4°C when the above
components have stabilized.
1. Press the Stop key on the UCM-
CLD.The compressors will
continue to operate and, after
unloading for 20 seconds, will stop
when the compressor contactor
de-energizes.
Subcooling
ƽ CAUTION
Normal subcooling for each circuit
ranges from 8-10°C, depending on
the units. If subcooling for either
circuit does not fall within these
values, check the overheating for the
circuit and adjust if necessary. If
overheating is normal but
During an extended shutdown
period, especially over the winter
season, the evaporator must be
drained of water, if the chilled water
loop does not contain glycol, to
prevent any risk of evaporator freeze-
up.
2) Stop the water circulation by
disconnecting the power supply to
the chilled water and cooling
water pumps.
subcooling is not, contact a qualified
service technician.
ƽ CAUTION
System Restart After Extended
Shutdown
Under freezing conditions, the chilled
water pump must remain in
operation during the full shutdown
period of the chiller if the chilled
water loop does not contain glycol,
to prevent any risk of evaporator
freeze-up.
Seasonal Unit Start-up
1. Close all valves and reinstall the
drain plugs in the evaporator.
1. Verify that the liquid-line service
valves, oil line, compressor
discharge service valves, and
suction service valves are open
(backseated).
2. Service the auxiliary equipment
according to the startup and
maintenance instructions provided
by the respective equipment
manufacturers.
ƽ CAUTION
Extended period shutdown
The procedure below must be
performed if the system has to be
stopped for a prolonged period, for
example seasonal shutdown.
To prevent damage to the
compressor, ensure that all
refrigerant valves are open before
starting the unit.
3. Close the vents in the evaporator
chilled-water circuits.
4. Open all the valves in the
evaporator chilled-water circuits.
1.Test the unit for refrigerant leakage
and repair as necessary.
2. Check the oil separator oil level
(see Maintenance section).
5. Open all refrigerant valves to
verify they are in the open
condition.
2. Open the electrical disconnect
switches for the chilled-water
pump. Lock the switches in the
"Open" position.
3. Fill the evaporator water circuit.
Vent the system while it is being
filled. Open the vent on the top of
the evaporator and condenser
while filling, and close it when
filling is completed.
6. If the evaporator was previously
drained, vent and fill the
evaporator and chilled-water
circuit. When all air is removed
from the system (including each
pass), install the vent plugs in the
evaporator water boxes.
ƽ CAUTION
Lock the chilled-water pump
disconnects open to prevent pump
damage.
ƽ CAUTION
Do not use untreated or improperly
treated water. Equipment damage
may occur.
4. Close the fused-disconnect
switches that provide power to the
chilled-water pump.
3. Close all chilled-water supply
valves. Drain the water from the
evaporator.
ƽ CAUTION
Ensure that the compressor and oil-
separator heaters have been
operating for a minimum of 24 hours
before starting. Failure to do so may
result in equipment damage.
4. Open the unit main electrical
disconnect and unit-mounted
disconnect (if installed) and lock in
the "Open" position. If the optional
control-power transformer is not
installed, open and lock the 115 V
disconnect.
5. Start the evaporator water pump
and, while water is circulating,
inspect all piping for leakage.
Make any necessary repairs before
starting the unit.
7. Check the adjustment and
operation of each safety and
operating control.
8. Close all disconnect switches.
6. While the water is circulating,
adjust the water flows and check
the water pressure drops through
the evaporator. Refer to "Water-
ƽ CAUTION
Lock the disconnects in the "Open"
position to prevent accidental startup
9. Refer to the sequence for daily
unit startup for the remainder of
the seasonal startup.
RLC-SVX03A-E4
23
Download from Www.Somanuals.com. All Manuals Search And Download.
Operation
System Flow Rates" and "Water-
System Pressure Drop."
7. Adjust the flow switch on the
evaporator piping for proper
operation.
8. Stop the water pump.The unit is
now ready for startup as described
in "Startup Procedures."
24
RLC-SVX03A-E4
Download from Www.Somanuals.com. All Manuals Search And Download.
Maintenance
Perform all maintenance procedures
and inspections at the recommended
intervals.This will prolong the life of
the chiller and minimize the
possibility of costly failures. After the
unit has been operating for
approximately 30 minutes and the
system has stabilized, check the
operating conditions and complete
the following procedures:
components for deficiencies.
Chemical Cleaning of the Evaporator
(RTUB)
5. Inspect all piping components for
leakage and damage. Clean out
any inline strainers.
The chilled water circuit is a closed
circuit, and therefore should not
accumulate scale or sludge. If the
chiller becomes obstructed, you can
attempt to unblock it by reversing
the water flow direction. If
6. Clean and repaint any areas that
show signs of corrosion.
7. Clean the condenser coils.
unsuccessful after several attempts,
clean the evaporator chemically.
ƽ WARNING
Weekly Maintenance
While the unit is running in stable
conditions:
Position all electrical disconnects in
the "Open" position and lock them
to prevent injury or death due to
electrical shock.
ƽ WARNING
Do not use an acid cleaning product
which might damage steel,
galvanized steel, polypropylene and
copper parts.
Contact a local water treatment
company advice on a suitable
chemical product for this unit. The
supplier of the cleaning product
must supply or approve:
1. Check the UCM pressure for
Evaporator, Condenser, and
Intermediate Oil.
8. Check and tighten all electrical
connections as necessary.
2.Measure the subcooling entering
the EXV.The subcooling should
never be less than 2.2°C under any
circumstances.
Coil Maintenance
Because seacoast applications are
considered to be a "dirty"
environment for condenser coils, it is
logical that the coils will need to be
cleaned more often than a coil
located inland. Cleaning four times a
year may be required or even more if
conditions are very poor or if
corrosion damage begins to occur.
To clean the coils, use a soft brush
and a sprayer (garden pump-up
type). A high-quality detergent, such
as "Trane Coil Cleaner, CHM0021" is
recommended for both standard and
coils with aluminium coating.
Follow the directions included with
the detergent. The most effective
method of coil cleaning is to remove
the condenser end panels and clean
the coils from the inside out using
the sprayer.
• All devices used in the circuit
ƽ CAUTION
Also check the rest of the system
operating conditions.
•The quantity of chemical product to
use
•The duration for which the chemical
product must circulate in the
evaporator
3. Inspect the entire system for
unusual conditions and inspect the
condenser coils for dirt and debris.
If the coils are dirty, refer to coil
cleaning.
• Safety precautions and
recommendations for using and
handling the chemical product
Monthly Maintenance
1. Perform all weekly maintenance
procedures.
Replacing the Oil Filter
Note: Routine changing of the oil or
oil filter is not recommended. The oil
filter is oversized for this application
and should not require replacement.
The oil and filter should be replaced
only if analysis reveals that the oil is
contaminated. Oil type and system
capacities are shown inTable 1.
Pressure drop across the oil filter is
shown in Figure 15. Oil filter
pressure drop is the difference
between the two pressure-control
ports.
2. Record the system subcooling.
3. Record the system superheat.
4. Make any repairs necessary.
Annual Maintenance
1. Perform all weekly and monthly
procedures.
ƽ CAUTION
If the detergent used is strongly
alkaline (pH greater than 8.5), an
inhibitor must be added.
Rinse the coil thoroughly after
cleaning. Failure to completely flush
the detergent from the coil can result
in accelerated coil corrosion. Blow
excess water from the coil using low-
pressure air. The water used to clean
the coils should always be clean,
fresh water (it should not be
2. Check the oil sump oil level while
the unit is off.
Note: Routine changing of the oil is
not required. Use an oil analysis to
determine the condition of the oil.
To change the oil filter in the unit,
refer to Figure 15 and follow the
steps listed.
3. Have a qualified laboratory
perform a compressor oil analysis
to determine system moisture
content and acid level.This
analysis is a valuable diagnostic
tool.
brackish, or contain excessive
dissolved minerals, chlorine, or
water softener salts.)
4. Contact a qualified service
organization to leak-test the chiller,
to check operating and safety
controls, and to inspect electrical
RLC-SVX03A-E4
25
Download from Www.Somanuals.com. All Manuals Search And Download.
Maintenance
Figure 15 - Oil filter change
12. Charge the unit with refrigerant
R134a refer to charging
procedure).
For units with the discharge valve
option:
1. Close the angle valve placed on
the refrigerant liquid line to store
the refrigerant in the condenser.
1. Oil charging valve
2. Oil pressure control port
3. Oil pressure control port
2. After the compressor stops, close
the compressor discharge valve
and disconnect the unit.
Note: Do not make successive
vacuums by using the compressor.
Irreversible compressor damage
could occur.
3. Vacuum the remaining refrigerant
in the evaporator.
Figure 16 - Oil filter pressure drop
4. Remove the seven bolts on the oil
filter cover. A pan may be
necessary to catch any oil that is
released after the cover is
loosened.
Normal pressure drop
Maximum pressure drop
5. Remove the cover and the oil filter
element.
6. Install the new filter element.
7. Coat the new cover gasket with
refrigerant oil.
8. Install the cover plate and cover
plate gasket.
9. Install a new copper gasket under
the bolt head that had one at time
of removal. Replace all other bolts
and tighten to 89.5 Nm.
Condensing Pressure - Suction Pressure (bar)
For units without discharge valve
option
1. Shut off the compressor and
disconnect all electrical service to
the compressor.
8. Install a new copper gasket under
the bolt head that had one at time
of removal. Replace all other bolts
and tighten to 89.5 Nm.
10. Vacuum the refrigerant circuit at
500 micron and isolate the
vacuum pump.
11. Confirm that no moisture or leaks
are present by letting the vacuum
stand for 2 hours.The pressure
should not raise more than
250 microns.
9. Vacuum the refrigerant circuit at
500 micron and isolate the
vacuum pump.
2. Vacuum the refrigerant out of the
circuit.
3. Remove the seven bolts on the oil
filter cover. A pan may be
necessary to catch any oil that is
released after the cover is
loosened.
10. Confirm that no moisture or leaks
are present by letting the vacuum
stand for 2 hours.The pressure
should not raise more than
250 microns.
12. Charge the unit with oil, in a
quantity equal to what has been
removed, by using the charging
valve placed on the oil filter.
4. Remove the cover and the oil filter
element.
11. Charge the unit with oil, in a
quantity equal to what has been
removed, by using the charging
valve placed on the oil filter.
Note: the oil is very sensitive to
moisture. Use the oil immediately
after the oil can has been opened.
5. Install the new filter element.
6. Coat the new cover gasket with
refrigerant oil.
13. Open all the valves before
restarting the chiller.
Note: the oil is very sensitive to
moisture. Use the oil immediately
after the oil can has been opened.
7. Install the cover plate and cover
plate gasket.
26
RLC-SVX03A-E4
Download from Www.Somanuals.com. All Manuals Search And Download.
Maintenance
Some symptoms of a refrigerant
under-charged unit:
• Low subcooling
Checking the separator oil
level
Figure 17 - System Oil Specifications
• Larger-than-normal evaporator
approach temperatures (Leaving-
WaterTemperature - Saturated
EvaporatorTemperature)
• Low Evaporator-Refrigerant
Temperature Limit
• Low Refrigerant-Temperature
Cutout diagnostic
1 Oil separator
2Valve
3 ¼" refrigeration hose
4 Sight glass
• Fully-open expansion valve
5 Minimum oil level
6 Maximum oil level
• Possible whistling sound coming
from liquid line (due to high vapor
velocity)
• High Condenser + Subcooler
Pressure drop
Some symptoms of a refrigerant
over-charged unit:
• High subcooling
• Larger-than-normal condenser
approach temperatures (Entering-
Condenser SaturatedTemperature -
Entering-AirTemperature)
• Condenser Pressure Limit
• High-Pressure Cutout diagnostic
• More-than-normal number of fans
running
Follow the steps listed below and
refer to the notes listed in Figure 17.
1.Turn off the unit.
4. After the level has been
determined, remove the sight
glass and hoses.
• Erratic fan control
• Higher-than-normal compressor
power
2. Attach the hoses and sight glass to
the oil-separator Schrader valves,
as shown in Figure 17. Remove
non-condensables.
Refrigerant and Oil-Charge
Management
Proper oil and refrigerant charge is
essential for proper unit operation,
unit performance, and
environmental protection. Only
trained and licensed service personal
should service the unit.
• Very low discharge superheat at
startup
• Compressor rattle or grinding
sound at startup
3. After the unit has been off for
10 minutes, move the sight glass
up and down until the level can be
seen.
Some symptoms of an oil over-
charged unit:
• Larger-than-normal evaporator
approach temperatures (Leaving-
WaterTemperature - Saturated
EvaporatorTemperature)
• Low Evaporator-Refrigerant
Temperature Limit
• Low Refrigerant-Temperature
Cutout diagnostic
• Low unit capacity
Table 5 - Oil level limit
• Compressor rattle or grinding
sound
Oil separator diameter (mm)
152
90
155
203
120
205
254
145
235
Minimum oil level (mm)
Maximum oil level (mm)
• High oil-sump level after normal
shutdown
RLC-SVX03A-E4
27
Download from Www.Somanuals.com. All Manuals Search And Download.
Maintenance
Some symptoms of an oil under-
charged unit:
• Compressor rattle or grinding
sound
[9 mm] flare). Open the service
valve.
8. Remove the remainder of the
charge with the vacuum pump.
Recommendation: Do not pump
the remaining charge into the high
side.This may introduce non-
condensable gasses and other
contaminants into the unit.
2. Add 4.5 kg of refrigerant (R134a)
charge.
• Lower-than-normal pressure drop
through oil system
3. Close the valve, remove the
charging hose and start the unit.
Monitor subcooling.
• Seized or Welded Compressors
9.The low side and the compressor
may be serviced at this time.
• Low oil-sump level after normal
shutdown
4. If subcooling is still insufficient,
return to step number 2.
Returning the unit to running
condition:
1. Open all the valves.
• Lower-than-normal oil
concentrations in the evaporator
Note: Proper subcooling can be
determined from run-log history,
service experience, or by contacting
Trane technical service.The service
tool may include a calculation
module that determines the proper
subcooling for any operating
2. Manually open EXV for 15 minutes
to allow the refrigerant to drain to
the evaporator by gravity.
R134a Field-Charging
Procedure
Be certain that the electrical power to
the unit is disconnected before
performing this procedure.
3. Let the unit sit with heaters on to
drive refrigerant out of the oil and
warm up the compressor
condition (Trane Service only).
bearings. Depending upon
ambient conditions, this may take
up to 24 hours.
Charge Isolation in the high
or low side of the system
ƽ WARNING
Position all electrical disconnects in
the "Open" position and lock them to
prevent injury or death due to
electrocution. Follow this procedure
when the unit is empty of all
refrigerant and under a vacuum.
All the refrigerant may be trapped
into the high side (condenser) of the
unit for maintenance on the
4. After the oil level has returned to
normal, the unit can be put back
into operation.
compressor (or low side). With the
suction-line service valve option,
charge may also be isolated in the
evaporator for maintenance on the
compressor (or high side). It is much
more preferable to isolate the charge
in the evaporator, if this option is
available.
Low-side charge-isolation procedure:
After normal shutdown, most of the
charge resides in the evaporator.
Running cold water through the
evaporator may also drive much of
the refrigerant to the evaporator.
1. Make sure the circuit is off.
ƽ CAUTION
Water must be flowing through the
evaporator during the entire
charging process to avoid freezing
and rupturing of the evaporator
tubes.
High side charge isolation procedure:
1. Make sure the circuit is off.
2. Close the suction-line isolation
valve.
1. Find the weight of the amount of
charge given inTable 1.
2. Shut the liquid-line service valve.
3. Close the oil return-line service
valve.
2. Attach the charging hose to the
evaporator service valve (3/8"
[9 mm] flare). Open the service
valve.
3. Shut the oil return-line service
valve.
4. Close the liquid line service valve.
5. Manually open the EXV.
4. Start the circuit with the service
tool in charge-isolation mode:
6. Use a liquid pump or vacuum
pump to move refrigerant from
the condenser to the evaporator.
3. Add charge to the evaporator to
bring the total circuit charge up to
the level given inTable 1.
• All fans will turn on
• EXV will open 100%
•The oil return-line solenoid will
open
The liquid pump will only be
4. Close the service valve and
disconnect the charging hose.
effective if there is a lot of charge in
the condenser. It may be connected
to the condenser drain port on the
liquid-line isolation valve.
•The unit will start at minimum load
Adding charge
This procedure should be followed
when adding charge to an
undercharged unit. When low charge
is indicated by low subcooling in the
liquid line, charge should be added
until sufficient subcooling is
achieved.
•The unit will run until it cuts out on
low pressure (~6 psia) [0.41 bar].
Note: if a pump is to be used,
5. When the unit trips, the discharge
check valve and the oil-line shutoff
valve close.
connect it before closing this valve.
This port is only isolated when the
valve is backseated. If a vacuum
pump is used, then connect it to the
discharge-line service valve near the
oil separator. A vacuum pump will be
required for part of the procedure.
6. Close the discharge isolation
valve.
1. Attach the charging hose to the
evaporator service valve (3/8"
7. Close the oil-line shutoff valve.
28
RLC-SVX03A-E4
Download from Www.Somanuals.com. All Manuals Search And Download.
Maintenance
The evaporator is large enough to
hold all the charge, for any unit,
below the centerline of the shell.
Therefore, no special precautions are
required to restart the unit after
isolating the charge in the
12. Attach the vacuum hose and
evacuate the liquid line.
• Oil line drain (lowest point in
system)
13. Remove the vacuum hose from
the liquid line and attach the
charging hose.
• Oil cooler
• Oil temperature sensor
• Oil line shutoff valve with flare
service connection
14. Replace the stored charge in the
liquid line.
evaporator.
• Oil filter (internal to compressor)
with flare-fitting service connection
and Schrader valve
Filter Replacement
Procedure
15. Remove the charging hose.
16. Open the liquid-line isolation
valve. On units with remote
evaporators or oil cooler circuits,
open the oil cooler liquid-line ball
valve.
A dirty filter is indicated by a
temperature gradient across the
filter, corresponding to a pressure
drop. If the temperature downstream
of the filter is 8°F [4.4°C] lower than
the upstream temperature, the filter
should be replaced. A temperature
drop can also indicate that the unit is
undercharged. Ensure proper
subcooling before taking
• Oil flow-control valve (internal to
the compressor after the filter)
• Oil return line from evaporator with
shutoff valve, strainer, and solenoid
control valve.The standard oil
charge for each circuit size is shown
inTable 1.
Lubrication System
The lubrication system has been
designed to keep most of the oil
lines filled with oil as long as there is
a proper oil level in the oil sump.The
total oil charge can be removed by
draining the oil system, the oil return
line from the evaporator, the
evaporator, and the compressor. Very
small quantities of oil may be found
in other components.
Measuring the oil level
1.To measure the oil level, use the
oil drain valve on the oil line and a
service valve on the discharge line.
This measurement can only be
made when the circuit is not
running. Note: the bottom plate of
the oil separator is approximately
1" [25 mm] thick.
temperature readings.
1. With the unit off, verify that the
EXV is closed. Close the liquid-line
isolation valve. On units with
remote evaporators or oil cooling
circuits, close the ball valve on the
oil cooler liquid line.
Oil Charging Procedure
Proper charging of the oil system is
critical to the reliability of the
2. Attach the vacuum hose to the
service port on the liquid-line filter
flange.
2.The initial oil charge should be
approximately at the level as
shown inTable 6.This is the
approximate oil level if all the oil is
in the oil lines, filter, and oil sump,
and the unit is in vacuum so that
there is no refrigerant dissolved in
the oil.
compressor and chiller.Too little oil
can cause the compressor to run hot
and inefficiently. When taken to an
extreme, low oil level may result in
infant failure of the compressor.Too
much oil will result in high oil-
circulation rates, which will foul the
condenser and evaporator
performance.This will result in
inefficient operation of the chiller.
Taken to an extreme, high oil levels
may result in erratic expansion-valve
control or shut down of the chiller
due to low evaporator-refrigerant
temperature.Too much oil may
contribute to long-term bearing
wear. Additionally, excessive
3. Evacuate the refrigerant from the
liquid-line and store.
4. Remove the vacuum hose.
5. Depress the Schrader valve to
equalize pressure in the liquid line
with atmospheric pressure.
3. After the unit has run for a while,
the oil level in the sump can vary
greatly.
6. Remove the bolts that retain the
filter flange.
The field-charging procedure
depends on the circumstances that
resulted in the need for oil charge.
1. Some service procedures may
result in loss of small quantities of
oil that must be replaced (oil
analysis, compressor filter
7. Remove the old filter element.
8. Inspect the replacement filter
element and lubricate the o-ring
withTrane OIL00048.
ƽ CAUTION
Do not use mineral oil. It will
contaminate the system.
replacement, re-tubing the
evaporator, and so forth).
compressor wear is probable when
the compressor is started with the oil
lines dry. Oil system consists of the
following components:
2. Additionally, some maintenance
procedures may result in virtually
all of the oil being removed
(compressor motor burn or total
removal of the charge to trouble-
shoot a unit).
9. Install the new filter element in the
filter housing.
• Compressor
10. Inspect the flange gasket and
replace it with a new one if
damaged.
• Oil separator
• Discharge line with service valve
11. Install the flange and torque the
bolts to 14-16 lb-ft [19-22 n-m].
3. Finally, leaks may result in a loss
of oil that must be replaced.
• Oil line from separator to
compressor
RLC-SVX03A-E4
29
Download from Www.Somanuals.com. All Manuals Search And Download.
Maintenance
Factory (initial) Oil-Charging
Procedure
The initial charging procedure
should be followed any time the unit
is new or has had all of the oil
removed.
1. Add 0.95 liter (0.90 kg) of oil to the
motor cavity or suction line prior
to installing the compressor into
the chiller.
oil-charging hose to the oil-
charging fitting and the other end
to an oil pump. Use the pump to
draw oil out of the oil container and
push the required amount of oil
into the unit. Note: the compressor
filter has an internal shutoff valve
that will prevent oil from entering
the compressor while the
compressor is not running.
Therefore, there is no concern
about flooding the compressor with
oil.
shutoff valve is closed. Other
compressor isolation valves may
also be closed depending upon
the service that was completed.
For example, changing the oil filter
would require the compressor to be
isolated and pulled into vacuum.
Note: Ensure that the compressor is
not pressurized.
3. Open the flare fitting on the oil-line
shutoff valve.
2. If the unit is not equipped with
suction-line isolation valves, it
should contain no charge. If it has
isolation valves, then the charge
may be trapped in the evaporator.
In either case, the high side of the
system should not be pressurized.
4. Open the flare fitting on the filter
housing.This is the port that must
be used to put oil into the
compressor.
Field Oil-Charging
Procedure
Use the initial charging procedure
under the following circumstances:
5. Install one end of the charging
hose on the oil charging port (with
the Schrader valve) and the other
on the oil canister.
3.The oil-line shutoff valve must be
open to allow the oil to pass into
the oil lines and the oil separator.
• When virtually all of the oil has
been removed.
6. Lift the oil canister, or use a pump,
to pour oil into the filter housing.
4.The oil charging port is a ¼"
[6 mm] flare fitting with a Schrader
valve that is on the side of the oil-
filter housing.This is the port that
must be used to add oil into the
compressor so that the filter and
lines are full at the first start of the
compressor.
• If the oil charge is removed from
the compressor and oil system
only, but the unit has been run for
less than 15 minutes.
7. When oil comes out of the flare
fitting on the oil-line shutoff valve,
the filter is full. Stop adding oil.
• If the oil charge is removed from
the compressor and oil system
only, and the unit has been run for
more than 15 minutes.
8. Put the cap on the flare on the oil-
line shutoff valve, remove the
charging hose, and put the cap
back on the flare on the filter
housing.
5. On single-compressor circuits, all
the oil should be put into the
circuit through the oil-charging
port on the compressor filter
housing. On two-compressor
circuits, put approximately ½ of
the oil into the unit through each
of the two oil-charging ports on
the two compressors.
However, reduce the amount of oil
added to the unit by the normal
quantity of oil in the refrigeration
system.
9. Vacuum the compressor (low side)
and prepare it for inclusion in the
system.There is a service valve on
the suction line and on the
evaporator. Use these valves to
vacuum the compressor.
Note: this procedure can be followed
even with the refrigerant charge
isolated in the evaporating section of
the unit.
10. Open the oil-line shutoff valve.
Severe damage to the
If small quantities of oil were
removed to service refrigeration
components, such as the evaporator,
replace the oil that was removed
back into the serviced component
prior to vacuum and recharge of the
refrigerant.
6. Oil may be put into the unit using
either of two methods:
compressor can result if the oil-
line shutoff valve is closed when
the compressor is started.
ƽ CAUTION
Use onlyTrane OIL 00048 in the units
to avoid any catastrophic damage to
the compressor or unit.
ƽ CAUTION
Catastrophic damage to the
compressor will occur if the oil-line
shutoff valve or the isolation valves
are left closed on unit startup.
If oil was removed to service a
compressor or change the filter
follow this procedure:
• Have the unit in vacuum. Note that
the vacuum connection should be
made on the unit at the service
valve that is on the discharge line.
Hook up one end of the oil-charging
hose to the oil-charging fitting and
immerse the other end into the oil
container. Let the vacuum draw the
required amount of oil into the unit.
1. If the compressor is a new
11. Open the other compressor
isolation valves.
compressor or has been removed
from the system and reworked,
add 0.95 liter (0.90 kg) of oil to the
motor cavity prior to installing the
compressor into the chiller.
Note: this procedure assumes that
the oil that is put into the filter
housing does not have contaminants
such as non- condensable gases.The
oil forces these gases out of the filter
2. Install the compressor in the
system. Make sure that the filter
• Have the unit at the same pressure
as the oil. Hook up one end of the
30
RLC-SVX03A-E4
Download from Www.Somanuals.com. All Manuals Search And Download.
Maintenance
and oil- line shutoff valve, without
the need to pull a vacuum on this
small volume. If the oil has been in
an open container or is otherwise
contaminated, then this small
volume must be subject to vacuum
as well. However, the filter cavity is
full of oil.Therefore, be sure to use a
flash tank in line with the vacuum
pump to ensure that the oil that is
pulled out of the filter cavity does
not slug the vacuum pump.
RLC-SVX03A-E4
31
Download from Www.Somanuals.com. All Manuals Search And Download.
Safety recommendations
Maintenance contract
Training
To avoid accidents and damage, the
following recommendations should
be observed during maintenance
and service visits.
It is strongly recommended that you
sign a maintenance contract with
your local Service Agency.This
contract provides regular
The equipment described in this
manual is the result of many years of
research and continuous
development.To assist you in
maintenance of your installation by a
specialist in our equipment. Regular
maintenance ensures that any
malfunction is detected and
obtaining the best use of it, and
maintaining it in perfect operating
condition over a long period of time,
the constructor has at your disposal
a refrigeration and air conditioning
service school.The principal aim of
this is to give operators and
maintenance technicians a better
knowledge of the equipment they
are using, or that is under their
charge. Emphasis is particularly
given to the importance of periodic
checks on the unit operating
1.The maximum allowable pressures
for system leak testing on low and
high pressure side are given in the
chapter "Installation". Always
corrected in good time and
provide a pressure regulator.
minimizes the possibility that serious
damage will occur. Finally, regular
maintenance ensures the maximum
operating life of your equipment. We
would remind you that failure to
respect these installation and
maintenance instructions may result
in immediate cancellation of the
warranty.
2. Disconnect the main supply before
any servicing on the unit.
3. Service work on the refrigeration
system and the electrical system
should be carried out only by
qualified and experienced
personnel.
parameters as well as on preventive
maintenance, which reduces the cost
of owning the unit by avoiding
serious and costly breakdown.
Literature Order Number
Date
RLC-SVX03A-E4
0202
Supersedes
B20IM004-E 0400
Europe
Stocking Location
Trane has a policy of continuous product and product data improvement and reserves the right to
change design and specifications without notice. Only qualified technicians should perform the
installation and servicing of equipment referred to in this publication.
TheTrane Company
An American Standard Company
For more information contact
your local sales office or
e-mail us at [email protected]
SociétéTrane – Société Anonyme au capital de 61 005 000 Euros – Siège Social: 1 rue des Amériques –
88190 Golbey – France – Siret 306 050 188-00011 – RSC Epinal B 306 050 188
Numéro d’identification taxe intracommunautaire: FR 83 3060501888
Download from Www.Somanuals.com. All Manuals Search And Download.
|