Q-DUAL WATER LEVEL PROBE (WLP)  
Installation Instructions for Kit 76-0293-3  
Ice machines which presently have the Q-Model Water Level Probe mounted on the front of the water  
trough. This will relocate the water level probe to the back wall of the ice machine.  
1. Place toggle switch in OFF position, move the switch back to  
ICE for 40 seconds to remove the water from the sump  
trough, and then turn the switch back to OFF.  
2. Disconnect power to the ice machine at the main disconnect.  
3. Remove the Q-model probe from the bracket on the front of  
the sump trough and disconnect the blue wire from the  
terminal labeled “WTR LEVEL” on the control board.  
4. Disconnect and remove the water pump.  
7. Route the WLP wire through the 1/2” hole and secure the  
WLP with supplied stainless steel screw.  
8. Route blue WLP wire to control box running it along the  
right side of the bulkhead and behind the receiver tank  
(removal of the back panel may be necessary).  
WARNING  
Blue water level probe wire must not contact line voltage  
wiring and must enter the bottom of the control box at the  
same location as the bin switch and ice thickness probe  
wiring.  
5. Mark WLP relocation point:  
A. Use the template on the next page to mark the correct  
position for the new WLP. **Prior to serial number,  
020200000, the template is not needed - holes have  
been drilled.**  
B. Align water pump holes with template and then place  
two marks on the back wall to the right of the water  
pump.  
9. Verify the WLP does not contact the water pump bracket.  
Bend the water pump bracket forward, if additional  
clearance is necessary.  
10. Verify the RIGHT water curtain does not hang on the  
WLP. Swing the curtain open completely and push it  
slightly toward the WLP. If the curtain catches on the  
WLP, the water curtain MUST be trimmed on the LEFT  
side (opposite side of the magnet). DO NOT trim, if the  
curtain swings freely.  
6. A refrigerant line may be located directly behind the  
previously marked location. Use a drill stop and drill two  
holes at the marked locations. The top hole will be a 1/8”  
hole; the bottom hole will be 1/2” in diameter.  
11. Use a file, grinder, or snips, to remove just enough of the  
water curtain to allow it to swing freely (see diagram  
below). Repeat Step 8 until the curtain clears the WLP.  
12. For further detail or questions about trimming the curtain,  
call Manitowoc Service Department at 1-800-545-5720.  
13. Verify no metal shavings exist in the food zone.  
14. Reapply power and test run one complete cycle.  
WARNING  
Use a suitable means to capture, contain, and remove all  
metal shavings produced during the drilling process.  
New Location  
for WLP  
Trim Here  
Right Hand Side Water Curtain  
Manitowoc Ice, Inc.  
2110 South 26th Street, P.O. Box 1720, Manitowoc, WI 54221-1720 USA  
Telephone 920-682-0161, Fax - Sales: 920-683-7589, Service/Parts: 920-683-7585, Other: 920-683-7879  
8016353  
Sheet 1 of 2  
Rev. 09/28/05  
Download from Www.Somanuals.com. All Manuals Search And Download.  

La Crosse Technology Thermometer IR 101 User Manual
Land Pride Lawn Mower RBT1560 User Manual
Lanzar Car Audio Car Amplifier MXA1600 User Manual
LevelOne Switch GSW 2496 User Manual
Mackie Musical Toy Instrument 1642 User Manual
Makita Cordless Saw 4304T User Manual
Makita Cordless Saw LS0714 User Manual
Makita Grinder 906H User Manual
Martin Audio Portable Speaker W8CT User Manual
Master Appliance Welder GT 70 User Manual