QUICK INSTALLATION GUIDE
COMMISSIONING OF THYRO-POWER MANAGER
Quick Installation Guide, valid is only the actual AEG Power Solutions operating manual of
Thyro-Power Managers (No. 8.000.024.628).
Thyro-Power
Manager
CONTENTS
1. Connection for voltage supply
2. Network Load Optimization
3. Additional Measurement Device
4. Safety Notes
5. Operation
6. Contact
EN
1. CONNECTION FOR VOLTAGE SUPPLY
Figure 1: Connection diagram for voltage supply 230V~; 50/60 Hz
Download from Www.Somanuals.com. All Manuals Search And Download.
5
6
The load resistance also has to be connected externally to the current converters. Within
standard default setting the following measurement values are read out: output 1 -
measurement value 1, output 2 - measurement value 2, output 3 - measurement value 3.
The following figure displays the principle structure and the connection diagram if using as
additional measurement device.
potentiometer is set on right stop, whereby 100% meaning 1V~ at the measurement inputs /
load resistances.
4. SAFETY NOTES
The commissioning of the unit is permitted only upon expert installation!
For this see the currently valid AEG Power Solutions operating manual
of Thyro-Power Manager.
5. OPERATION
Mains voltage - Danger!
Activate the unit only if it is secured that all necessary measures for
protection against electric shock are implemented.
5.1. REGULAR OPERATION
Enabling mains voltage during regular operation activates the unit. Subsequently, the green
power LED H100 and the green ON LED H101 should burn. If network load optimization is
used, the LEDs H201 - H210 turn ON one after another (contingent to the selected number).
All measurements and functions are performed as selected.
For more information and integration of software for programming, measurement and
indication please see our comprehensive and actual valid operations manual.
Figure 5: Connection Diagram for Additional Measurement Device
3.2. SETTING THE NETWORK PEAK LOAD MONITORING /
MEASUREMENTS:
No settings are necessary for the additional measurement device. Converters or load
resistances have to be configured in a manner so that a 1V~ measurement voltage is
generated at a nominal electrical current. Thus, a voltage of 10V- results at the respective
analog output.
3.3. SETTING THE LIMITING VALUE FOR MONITORING
If the additional measurement device is also used as network peak load monitoring, limiting
value could be set via the help of the potentiometer R310. Standard setting is 200%, the
Download from Www.Somanuals.com. All Manuals Search And Download.
7
6. CONTACT
TECHNICAL QUERIES
If you have any technical queries regarding the subjects dealt with in these operating
instructions, please get in touch with our team for power controllers:
Phone: +49 (0) 2902 763-520
COMMERCIAL QUERIES
If you have any commercial queries on power controllers, please get in touch with:
Phone: +49 (0) 2902 763-558
SERVICE-HOTLINE
Our team is at your service on the following hotline:
Phone: +49 (0) 2902 763-600
INTERNET
Further information about our company or products please visit:
6.1. COPYRIGHT
The forwarding, copying and/or receipt of this operations manual via electronic or
mechanical means, even in part, requires the expressive prior and written approval of AEG
PS.
© Copyright AEG Power Solutions GmbH 2013.
All rights reserved.
BETRIEBSANLEITUNG/ OPERATING INSTRUCTIONS
DE/EN, 08/13 – V1
6.2. FURTHER INFORMATION ON COPYRIGHT
Thyro- is an international registered trademark of AEG Power Solutions GmbH.
All other company and product names are (registered) trademarks of the respective owners.
Due to our policy of continuous development, the data in this document is subject to
change without notice.
AEG is a registered trademark used under license from AB Electrolux.
EMIL-SIEPMANN-STR. 32
59581 WARSTEIN-BELECKE - GERMANY
TEL.: +49 2902 763 -520/ -290 - FAX: +49 2902 763 1201
WWW.AEGPOWERCONTROLLERS.COM
Download from Www.Somanuals.com. All Manuals Search And Download.
|